The project of Gustav's cape 2 involves the establishment of a new surface for short-term storage of goods in the port - an area of approximately 9,000 m2.
The contractor NCC, which is carrying out the work, will excavate and fill the surface north of the Feed Center. The surface is provided with a gravel wear layer.
Construction time: December 2020 - January 2021.
The map shows the work area for project Gustav's cape 2, as well as the contractor NCC's establishment in the port.
The weather conditions at the worksite are very tough right now, a lot of snow and wind.
Workforce: 1 worker, 1 supervisor/surveyor, 1 wheel loader, 4 trucks.
Preparation for blasting stone
Workforce: 1 worker, 1 supervisor/surveyor, 1 excavator, 1 wheel loaders, 4 trucks, 1 dumper.
Workforce: 1 worker, 1 supervisor/surveyor, 1 excavator, 1 wheel loaders, 3-4 trucks, 1 dumper.
Workforce: 1 worker, 1 supervisor/surveyor, 1 excavator, 1 wheel loaders, 2-4 trucks, 2 dumpers.
Workforce: 1 worker, 1 supervisor/surveyor, 1 excavator, 1 wheel loaders, 2-4 trucks, 2 dumpers.
Establishment is complete and road closures/road signs are placed in the area. Excavation has begun.
Workforce: 1 worker, 1 supervisor/surveyor, 1 excavator, 1 wheel loaders, 2 trucks, 2 dumpers.
• Establishement of contractor, NCC.
• putting out closures and road signs.
• Excavation is expected to begin at the end of the week.
Workforce: 1 worker, 1 supervisor, 1 excavator, 1 wheel loaders and varying number of trucks/dump trucks.